"As Çalık Enerji's first turnkey EPC Combined Cycle Power Plant, the construction of Gardabani project is in full spate. Currently providing 570 people with employment, the project marked 55 % progress by the end of August, and kept pace since then. 49 % of procured equipment items has been delivered on the site while it is estimated to deliver an additional 37 % on the site around September/October, 2014. Transformer mounting components (2 pieces of 80/100 MVA, 1 piece 90/110 MVA and 2 pieces of 15 MVA), which are major milestones for the project, are now on the site, and smoothly mounted.
The project is currently in progress in line with a business mentality making no concession on quality and experiencing no occupational accident with loss of time. Carrying on thanks to tremendous effort and self-sacrifice of the employees, the project is estimated to draw to a close prior to October 2015 stipulated by the contract."