Within our 504.4 MW simple cycle power plant project carried out in Derweze district in the Ahal region of Turkmenistan, synchronization of GT-4 unit was successfully completed on August 25, 2015.
Thus, by generating energy from all the 4 turbine units in the project, the electric conduction was delivered through 110-220 kV switchyards and transmission and distribution lines to the required areas. The next step right after the completion of synchronization, which is to conduct 72-hour safe working tests, was also successfully completed in 4 turbine units.
We would like to thank all of our staff that exerted their efforts tor render 4 gas turbines operational in a highly short time- in approximately 10 months.