  • Project Title : Mary-3 Combined Cycle Power Plant
  • Capacity : 1.574 MW
  • Equipment : 4xSingle-Fuel GE F.03 Multi-Shaft Gas Turbines + 4 x HP-LP HRSG + 2 x St​eam Turbines
  • Voltage Level : 500 kV & 220 kV
  • Commencement Date : July 2015
  • Date of Delivery : December 2018​
  • Employer : Ministry of Energy, Turkmenistan
  • Scope : Lump Sum Turnkey EPC Prime Contractor
​​​
  • 01.07.2015

Description of Project

We will supply and mount all ancillary equipment in addition to all main equipment required for operation of the power plant, and deliver it to the employer as a Turnkey project.

EPC contract includes all conceptual and detailed design, procurement of equipment, construction, and mounting of all mechanical, electricity, instrumental and control systems for the Power Plant. The contract also comprises operation tests, commissioning and training of employer's staff.