EPC Power Systems

Navoi Combined Cycle Power Plant


About Project

  • Project Title : Navoi Combined Cycle Power Plant
  • Capacity : 478 MW
  • Equipment : ​Mitsubishi Heavy Industries (MHI) Gas Turbine (M701F4), Nooter Ericsen Steam Turbine (TC2F-40.5)​​​​​​
  • Voltage Level : 220 kV
  • Commencement Date : August 2009
  • Date of Delivery : October 2012
  • Employer : Ministry of Energy, Uzbekistan
  • Scope : Turnkey Consortium Contractor
  • 08.10.2009

Description of Project

    Combined Cycle Power Plant

    EPC Main Contractor for 478 MW Navoi Power Plant

    Project Features:

    - The Very First Project of Çalık Enerji in Uzbekistan,

    - Uzbekistan's First Combined Cycle Power Plant,

    - Navoi meets 4 % of Uzbekistan's Energy Requirement,

    - The First and The Most Efficient CCPP Across the Asia,

    - Zero Loss in Distribution to 5 Countries,

    - Compliance with Russian and UK Standards.​