  • Project Title : Turkmenbashy Refinery Simple Cycle Power  Plant
  • Capacity : 126,4 MW
  • Equipment Spec : Simple Cycle, 3xGE-PG6581-B (Frame 6B)
  • Voltage Level : 35 kV & 110 kV
  •  Commencement Date : September 2001
  • Date of Delivery : May 2003
  • Employer : Ministry of Oil and Gas, Turkmenistan
  • Scope : Lump Sum Turnkey EPC Prime Contractor ​
  • 01.01.2002

Description of Project

    We supplied and mounted all ancillary equipment in addition to all main equipment required for operation of the power plant​ and delivered it to the employer as a turnkey project.

    EPC contract includes all conceptual and detailed design, procurement of equipment, construction, and mounting of all mechanical, electricity, instrumental and control systems for the power plant. The contract also comprises operation tests, commissioning and training of employer's staff.