EPC Power Systems

Balkanabat-2 Simple Cycle Power Plant


About Project

  • Project Title : Balkanabat-2 Simple Cycle Power Plant
  • Capacity : 254,2 MW
  • Equipment : Simple Cycle, 2xGE-PG9161-E (Frame 9E)
  • Voltage Level : 110 kV
  • Commencement Date : July 2008
  • Date of Delivery : April 2010
  • Employer : Ministry of Energy, Turkmenistan
  • Scope : Lump Sum Turnkey EPC Prime​ Contractor
  • 21.07.2008

Description of Project

We supplied and mounted all ancillary equipment in addition to all main equipment required for operation of the power plant  and delivered it to the employer as a Turnkey project.

EPC contract includes all conceptual and detailed design, procurement of equipment, construction, and mounting of all mechanical, electricity, instrumental and control systems for the Power Plant. The contract also comprises operation tests, commissioning and training of employer's staff.​​