Combined Cycle Electricity Generation Realized in Navoi-2 Project


Steam turbine synchronization and combined cycle full load electricity generation in our Navoi-2 Project was successfully realized as of 21 August 2019. Despite the serious delays caused by external factors, maximum effort was given during the initial phase of the project and the relevant milestone was reached 4 months earlier than the contract date. This project is also very important for our company as it is one of the first projects where all construction works are undertaken by Çalık Enerji's own teams.

The first phase of the project, simple cycle electricity generation, was realized in January 2019; the opening ceremony of the project is planned to be held within the next month.