Çalık Enerji

Steam Turbine & Generator On-Base Process Completed As Part Of Turakurgan Project


Turakurgan Combined Cycle Power Plant Project of which the construction works started in January 2017 continues at full steam.

ST & STG-1 (steam turbine & generator) on-base installation works have been completed in 29 November 2018 and ST & STG-2 (steam turbine & generator) on-base installation works have been completed in 23 December 2018 as part of the project. Current percentage of completion of the project is 62,40 % and contractual delivery date of the project is April 2020. ​


Çalık Enerji

Contact

  • Address: Büyükdere Cad. No:163 34394 Zincirlikuyu – Şişli / İstanbul

  • Phone: +90 (212) 306 50 08

  • Office hours: 8.30 a.m. - 6.00 p.m.

  • E-Mail: info@calikenerji.com