First Fire Performed in Navoi-2 Project


​First Fire and Full Speed No Load (FSNL) tests within the scope of Navoi-2 Project have been successfully performed in 29 December 2018.

Despite the 9-month delay stemming from the employer at the beginning of the project, Navoi-2 Project has been brought to its current level in a very short time by showing maximum effort. This project is also very important for our company as it is one of the first projects where all construction works are undertaken by Çalık Enerji's own teams.

Overall progress of our project is currently 80,39%. It is planned to commercially start-up simple cycle of the power plant in January 2019.