Gas Turbıne and Generator Installatıons as Part Of Navoı-2 Project Performed Successfully


Gas turbine and gas turbine generator installations as part of Navoi-2 450 MW Natural Gas Combined Cycle and 200 GCAL Heat Plant Project have been successfully completed on 9 - 10 June 2018.

As of today, we have two thousand employees who work for the Navoi-2 Project. Overall progress of the project is 39,3%. It is estimated that the equipment, tanks, pipes and electric-instrumentation works of the simple cycle will be completed in the third quarter of 2018 within the scope of the Project, under which the ACC and HRSG installation works will be initiated in the upcoming months. Following these activities, it is planned to make first fire in the fourth quarter and commission the power plant as a simple cycle at the end of the year. 